Public record · civil society tracker Current to 31 July 2026 · next date 12 Aug

Fujitsu
& the public purse

What the voluntary bidding pause actually commits Fujitsu to, what public money it has been awarded since, and what it has paid towards the Horizon redress bill. Built for campaigners, journalists and researchers — every figure traceable to a primary source.

The account that doesn't balance

Horizon redress · public vs. supplier

The Horizon scandal was caused by an accounting system that showed money missing when it wasn't. Here is a shortfall that is real: what the public has paid into redress, set against what the supplier at the centre of it has paid back.

Horizon redress — statement of account Period: 2020 → 26 June 2026
Paid out by the public
Funded by government / Post Office Ltd, i.e. by the taxpayer
Horizon Shortfall Scheme£995m
Convictions Redress Scheme£317m
Group Litigation Order scheme£233m
Overturned Convictions (closed)£68m
HSS Appeals£14m
Redress paid£1,628m
Est. total incl. legal & admin≈£2,000m
Recovered from Fujitsu
Contribution towards the cost of the scandal it supplied
Direct payments to sub-postmastersNIL
Interim payment on accountNIL
Provision in UK company accountsNIL
Figure agreed with governmentNONE
Deadline for agreeing oneNONE
Recovered£0
Redress talks openedMar 2025
Unreconciled Carried forward, 16 months after redress talks began
£1,628,000,000

Redress figures: DBT monthly publication, position as at 26 June 2026 — £1,628m paid to over 12,900 claimants. Total-cost estimate and the nil entries: Business and Trade Committee report, March 2026, and Fujitsu's own evidence to that committee that no provision has been made and no value discussed. Fujitsu has funded some non-financial support and is party to a restorative justice project; that is not counted here as redress.

Printing includes every tab, not just the one on screen.

Four things people assume are settled

None of them are
Bidding moratorium
Voluntary & self-defined

Not a government ban. Not in any contract or statute. Fujitsu wrote the terms, decides what falls inside them, and can end it — but it wrote them to cover all public procurements, expressly including frameworks and DPS. Six framework places later, MPs have asked the Secretary of State to explain. Reply due 12 August.

In place since January 2024
Public inquiry
1 of 6 volumes out

Volume 1 (human impact and redress) was published in July 2025. The remaining five volumes will be published together. Warning letters to those facing criticism have gone out for Volumes 2–3 only.

Chair, 8 July 2026: "some months away"
Debarment list
Fujitsu not on it

The Procurement Act 2023 created a public list of suppliers barred from public contracts. The Cabinet Office's Permanent Secretary confirmed to MPs in June 2026 that the power exists and can follow an investigation. None has been announced.

List in force since 24 February 2025
Criminal investigation
Waiting on the report

The Met's Operation Olympos has identified suspects and persons of interest but is holding charging recommendations until the inquiry's final report. A separate corporate manslaughter line of inquiry concerns the Post Office.

Ongoing since 2024

Things that sound made up

Every one is on the record

The hardest part of campaigning on this is that the true version sounds exaggerated. Each card below carries its source, because the first response to most of them is disbelief.

  • Fujitsu runs the communications link between Royal Navy submarines and headquarters.

    A minister listed it in the Lords as a reason government cannot simply stop using the company — alongside HMRC self-assessment and the Home Office border operation. Hansard records peers reacting audibly before he finished.

    Hansard · Lords · 17 Mar 2026
  • £1.63bn of public money has gone out. Nothing has come back.

    No payment to sub-postmasters, no interim sum, no provision in the UK accounts, no agreed figure and no deadline for agreeing one — more than a year after redress talks formally opened.

    DBT redress data · BTC report, Mar 2026
  • Fujitsu's auditors confirmed that is entirely lawful — because nobody has asked it to pay.

    Asked by MPs why no provision had been set aside, the auditors replied that concluding on provisioning is a matter for the directors, and the directors face no demand. The gap exists because no one has created a liability.

    Auditor letter to the BTC · Jan 2026
  • HMRC awarded £220m without competition because the systems sit on Fujitsu's own hardware.

    Its stated justification was that the applications are hosted and operated on Fujitsu infrastructure in Fujitsu datacentres with Fujitsu connectivity, so no other supplier could deliver. The lock-in was the reason for extending the lock-in.

    Award reported · Jun 2025
  • A £48m Police National Computer contract drew no other bidders at all.

    Awarded as a single tender action after the Home Office found nobody else had tendered for maintenance of the ageing national policing database.

    Home Office documents, reported
  • Horizon is still generating unexplained shortfalls today.

    The Post Office wrote off £11.6m of unidentified discrepancies recorded on Horizon in its most recent financial year, and £10.4m the year before. The system remains in branches, with parts of it potentially running to 2033.

    Post Office accounts · Computer Weekly
  • The Post Office spent more on one law firm at the inquiry than the inquiry cost.

    £83m went to its legal representatives between 2020 and 2025, plus £3m helping its own witnesses with their statements — more than double the cost of the public inquiry examining it. Disclosed only through a freedom of information request.

    FOI response · reported 2025
  • Fujitsu's own pledge names frameworks — and it has joined six since making it.

    The February 2024 letter to the Cabinet Office says the approach applies consistently to all public procurements, expressly including where goods and services are procured under a Framework Agreement or DPS. Winning a framework place is itself a public procurement. Fujitsu says a place only supports work with existing customers; the letter draws no such distinction.

    Letter terms read into the record · Q75–Q80
  • The debarment list is empty. Not Fujitsu-free — empty.

    The Procurement Act's central register of suppliers barred from public contracts went live in February 2025. No supplier of any kind has been added to it since, and no investigation into Fujitsu has been announced.

    Cabinet Office debarment list (PDF)
  • Three months into its own bidding pause, Fujitsu briefed staff on how to keep bidding within it.

    The company's UK public sector head — the same executive who had written to the Cabinet Office confirming there was no caveat on the pause — instructed staff on working inside its terms.

    Computer Weekly · Apr 2024
  • A senior Fujitsu figure reportedly judged the report linking the scandal to 13 suicides "not that bad".

    Volume 1 found a real possibility that thirteen people took their own lives as a result of their treatment. The remark was reported after publication.

    Computer Weekly · Oct 2025
  • Fujitsu's UK public sector revenue went up after the scandal broke.

    £453m in 2024/25, a 1% rise, in the year following the drama, the apologies and the bidding pause.

    Tussell report, via PublicTechnology · Oct 2025

Using these

Each card is deliberately short enough to quote and specific enough to check. Follow the source before you publish — several of these are widely repeated in garbled form, and a single wrong figure hands the other side the whole argument.